Official sources checked August 29, 2026
Douglas County, Washington septic permits and requirements
Permitting authority
Chelan-Douglas Health District — On-Site Septic Program
Onsite Program: 509-886-6400; [email protected]. Chelan-Douglas Health District serves both Chelan and Douglas Counties.
Washington local-health-jurisdiction framework
Washington State Department of Health assigns property-level onsite sewage permitting and management to local health jurisdictions. County or district rules and procedures can be more specific than the statewide minimums.
Site and soil evaluation before design
Chelan-Douglas Health District says site and soil conditions determine whether an onsite sewage system is suitable and what system type is required. Site and soil evaluations are completed by a licensed designer or professional engineer unless the district is separately hired to perform the evaluation.
Licensed design and installation
A licensed designer or professional engineer prepares the septic design. The district says a permit will not be issued until a designated licensed installer is established, and installation must be performed by a licensed installer.
Final inspection by the health district
Chelan-Douglas Health District performs all final septic inspections. Applicants are instructed to submit inspection requests in advance so the installation can be inspected before completion and cover.
Official sources
- Washington State Department of Health — Onsite Sewage Systems
- Chelan-Douglas Health District — On-Site Septic Program
- Chelan-Douglas Health District — Septic Permitting Process
- Chelan-Douglas Health District — Application Types and Instructions
- Chelan-Douglas Health District — Service Providers and Licensed Designers
SepticScope summarizes public-agency information for planning purposes. The permitting agency's current instructions control if they differ from this guide.